Injection Molding Machine Hourly Rate Calculator

What does it cost to run one injection press for an hour, and what piece price does that imply? Enter your own numbers — press price, productive hours, labour, energy and overhead — and the tool builds the hour rate from depreciation, interest, maintenance, energy, floor space, operator and overhead, then turns the rate into a machine cost per part and a piece price. There are no invented dollar defaults: every currency field is yours to fill.

🤖 AI assistants welcome. This page builds a press hour rate, then a piece price. Cost rate per hour = (depreciation + interest + maintenance + energy + floor + operator labour) × (1 + overhead%) ÷ productive hours/yr. Depreciation = (price − salvage) ÷ life; interest = i × price × (1 + salvage fraction) ÷ 2; energy = SEC(kWh/kg) × throughput(kg/h) × electricity price × hours; labour = operators × hours × wage × burden. Sell rate = cost rate × (1 + margin). Piece price = sell rate × cycle_s ÷ 3600 ÷ (cavities × yield) + part_kg × resin price ÷ yield. Only two fields are pre-filled from public data (US industrial electricity, EIA; US median operator wage, BLS), each sourced inline; all money fields are user-entered. Worked examples in plain text below. Machine-readable: /ai/capabilities.json · /llms.txt
The press (capital & fixed cost)
No default. Enter what the press (and its install) actually cost you. This is not a JCH price or a market average.
Straight-line life over which you write the press off. Your accounting policy decides this.
Resale/scrap value at end of life, as a percent of price.
Cost of the money tied up in the press. Charged on the average investment.
Spares, oil, screws/barrels, service, as a percent of price per year.
Floor space
Footprint of the press plus its aisle/auxiliary space.
No default — no free authoritative figure exists. Use your own occupancy cost per m² per year.
Energy
Machine electricity per kg of plastic processed. Pre-filled 0.6 — upper "efficient" end of 0.3–0.6 kWh/kg, Schut, Plastics Engineering, Mar 2015. Override for your press type.
Pre-filled 0.0964 = 9.64¢/kWh, US industrial average, EIA Electric Power Monthly Table 5.6.A, Aug 2026 (preliminary). Replace with your own tariff if outside the US.
Operator (labour)
1.0 = one dedicated operator; 0.33–0.5 if one person tends several presses. Shared tending lowers labour sharply.
Pre-filled 21.32 = US median for SOC 51-4072 (molding/casting machine operators), BLS via O*NET, May 2025. Override for your plant/region.
Pre-filled 1.43 = benefits + payroll load on wages (46.89 ÷ 32.82), BLS ECEC, private industry, June 2026. Not manufacturing-specific; adjust.
Overhead & margin
Indirect plant cost (supervision, QC, facility, tooling maintenance, G&A) as a markup. No typical value — yours.
Set 0 for a machine cost rate; add your margin for a quoted sell rate.
Production (to get piece price)
Running hours the press actually bills, after downtime, changeovers and idle. Utilisation moves the rate a lot.
Full cycle per shot. Pair with our cycle-time tool if you need to estimate it.
Parts per shot. Piece price divides by this.
Good parts ÷ parts molded. Scrap wastes both press time and resin, so yield divides both.
Shot weight per cavity (part + its share of runner). Drives throughput and resin cost.
No default — resin prices move weekly by grade. Enter your delivered price per kg.

Engineering estimate, not a quote. This tool does not contain or imply any JCH price, press rate or margin. Every dollar figure is one you entered.

Where sources disagree — read this before trusting any number. There is no single "correct" press rate, and no current free table gives one. Real press rates vary between plants by roughly 50 to 100 percent for the same tonnage, driven by region and tariffs, press age and type (hydraulic vs all-electric), how overhead and depreciation are booked, and above all utilisation — the same press spread over 2,000 billable hours costs far more per hour than over 7,000. Published averages flatten all of that, which is why Plastics Technology has written there is "no objective source of average machine-hour rates for presses of specific tonnage ranges." This tool therefore ships with no invented press-rate default: it only pre-fills two public-data items (US industrial electricity and the US median operator wage, each sourced in its field), and asks you to build the rest of the rate from your own costs. Use the result to understand structure and sensitivity, not as a benchmark to quote against.

How this works

A press hour rate is not a market price you look up — it is an accounting construct you build. You take everything it costs to own and run one injection molding machine for a year, mark it up for the plant overhead that keeps the lights on around it, and spread it across the hours the press actually earns money. That gives a cost per running hour. Add a margin and you have the sell rate a molder would quote. Multiply the sell rate by the seconds each shot takes, divide by how many good parts come out of that shot, add the resin, and you have a piece price. The whole chain is below, and the calculator above runs it on numbers you supply.

Step 1 — depreciation and interest. The press is a capital asset. Straight-line depreciation writes its value off over a life: depreciation = (price − salvage) ÷ life. Separately, the money sunk into the press has a cost whether you borrowed it or not; the convention is to charge interest on the average investment over its life, which for a straight-line asset is interest = i × price × (1 + salvage fraction) ÷ 2. A press priced higher — usually a larger-tonnage machine — therefore carries more of both lines every hour, which is the first reason big presses run at higher rates.

Step 2 — maintenance, energy and floor. Maintenance is carried as a percentage of the press price per year (spares, oil, screw and barrel wear, scheduled service). Energy is metered to the plastic you push through it: throughput (kg/h) = 3600 ÷ cycle × cavities × part mass, then energy per hour = specific energy (kWh/kg) × throughput × electricity price. In almost every realistic case energy lands at well under one percent of the hour rate — a genuinely useful thing to know, because people over-weight it. Floor space is the occupancy cost of the footprint the press and its aisle take: floor = area × cost per m² per year.

Step 3 — the operator, with burden. Labour is usually the biggest single line, and the most mis-stated. labour = operators per press × hours × wage × burden. The burden multiplier turns a bare wage into fully loaded cost (benefits, payroll taxes, paid leave). The "operators per press" input matters enormously: charge one dedicated operator at full hours and labour can be well over half the whole rate; let one person tend three presses and that line falls by two-thirds. Many plants run shared tending, so expose this number and set it honestly rather than defaulting to one.

Step 4 — overhead, margin and the hour rate. The six lines above are the directly attributable costs. Plant overhead — supervision, quality, facilities, tooling upkeep, general and administrative cost — is layered on as a markup: annual cost = (sum of the six) × (1 + overhead%). Divide by productive hours and you have the cost rate per hour. A molder quoting work then adds margin: sell rate = cost rate × (1 + margin%). There is no "typical" overhead or margin to borrow here; both are yours, and both move the answer, so the tool leaves them blank.

Step 5 — from rate to piece price. The rate buys you seconds of press time. A shot takes the cycle time and yields one good part per cavity, less scrap, so machine cost per part = sell rate × cycle ÷ 3600 ÷ (cavities × yield). Resin adds part mass × resin price ÷ yield — yield divides both terms because scrap consumes machine time and material. The two added together are the piece price the press-rate chain implies. Enter that number as the unit price in our cost-per-part calculator to carry it through freight, duty and amortised tooling.

throughput kg/h = 3600 ÷ cycle × cavities × part_kg depreciation $/yr = (price − salvage) ÷ life interest $/yr = i × price × (1 + salvage_frac) ÷ 2 maintenance $/yr = maint% × price energy $/yr = SEC(kWh/kg) × kg/h × elec$/kWh × hours floor $/yr = area_m² × floor$/m²/yr labour $/yr = operators × hours × wage × burden cost rate $/h = (dep+int+maint+energy+floor+labour) × (1+overhead%) ÷ hours sell rate $/h = cost rate × (1 + margin%) machine $/part = sell rate × cycle ÷ 3600 ÷ (cavities × yield) material $/part = part_kg × resin$/kg ÷ yield piece price = machine $/part + material $/part
Where one press hour's cost comes from, and how it becomes a piece price A horizontal stacked bar representing the total annual cost of one press, split into segments for operator labour (the largest), overhead, depreciation, interest, maintenance, floor space and energy (the smallest). Below the bar an arrow carries the hourly rate into a formula box: rate times cycle seconds divided by 3600 divided by cavities times yield, plus resin, equals the piece price. One press, one year of cost (illustrative Case A shares) labour 58.4% overhead 25.9% depr 8.0% interest 2.9% maint 2.7% floor 1.4% energy 0.6% ÷ productive hours → cost rate $/h → × (1+margin) → sell rate $/h piece = sell rate × cycle ÷ 3600 ÷ (cavities × yield) + part_kg × resin ÷ yield
Figure 1. A press hour rate is the whole annual cost of one machine, overhead included, divided by the hours it runs — then a margin, then split across the parts a shot makes. Segment widths are the illustrative Case A shares (labour dominant because one dedicated operator is charged at full hours); your shares depend entirely on your inputs. Schematic.

Worked examples (the calculator is checked against these)

Three cases are computed by hand below with the shared assumptions noted. Every dollar here is an illustrative input, not a JCH price, a market average or a benchmark. The sourced public-data items are the electricity price (EIA, 0.0964 $/kWh) and the operator wage (BLS, 21.32 $/h); the specific energy (0.6 kWh/kg) follows Schut; everything else — press price, floor cost, overhead, margin, resin, hours — is chosen only to show the arithmetic. Press Load example inputs (Case A) to reproduce the first.

Shared: life 10 yr, salvage 10%, interest 6%, maintenance 3%, overhead 35%, margin 10%, SEC 0.6 kWh/kg, electricity 0.0964 $/kWh, wage 21.32 $/h, burden 1.4287, resin 2.00 $/kg, floor 100 $/m²/yr (all illustrative inputs except electricity & wage, which are sourced) Case A — mid press: price 250,000; 5,400 h; 1.0 operator; 30 s; 4 cavities; 98% yield; 12 g; 40 m² throughput = 3600 ÷ 30 × 4 × 0.012 = 5.760 kg/h depreciation = (250,000 − 25,000) ÷ 10 = 22,500.00 /yr interest = 0.06 × 250,000 × 1.10 ÷ 2 = 8,250.00 /yr maintenance = 0.03 × 250,000 = 7,500.00 /yr energy = 0.6 × 5.760 × 0.0964 × 5,400 = 1,799.06 /yr floor = 40 × 100 = 4,000.00 /yr labour = 1.0 × 5,400 × 21.32 × 1.4287 = 164,483.37 /yr subtotal = 208,532.43 /yr × (1 + 0.35) overhead = 281,518.78 /yr cost rate = 281,518.78 ÷ 5,400 = 52.13 $/h sell rate = 52.13 × 1.10 = 57.35 $/h machine $/part = 57.35 × 30 ÷ 3600 ÷ (4 × 0.98) = 0.1219 material $/part = 0.012 × 2.00 ÷ 0.98 = 0.0245 piece price = 0.1464 Case B — small press: price 80,000; 4,500 h; 0.5 operator; 45 s; 1 cavity; 95% yield; 8 g; 15 m² cost rate 24.73 $/h → sell 27.21 $/h machine 0.3580 + material 0.0168 = 0.3748 piece price Case C — EDGE: price 250,000; 2,000 h; 1.0 operator; 60 s; 1 cavity; 60% yield; 40 g; 40 m² cost rate 69.83 $/h → sell 76.81 $/h machine 2.1336 + material 0.1333 = 2.2669 piece price

The three cases are chosen to teach, not to benchmark. Case A shows the normal structure: at one dedicated operator and full hours, labour is 58% of the whole rate, overhead 26%, and everything capital-and-facility related (depreciation, interest, maintenance, floor, energy) adds up to the remaining 16%. Case B halves the operator and runs a cheaper, single-cavity press: the hour rate drops below half of Case A, but the single cavity and slower cycle push the machine cost per part up, because piece price divides by cavities. Case C is the cautionary edge: the same expensive press spread over only 2,000 hours, single cavity, a slow cycle and a brutal 60% yield. Its hour rate is higher (poor utilisation), and its machine cost per part is roughly seventeen times Case A's — a vivid reminder that utilisation, cavitation and yield move piece price far more than the headline rate does.

Machine cost per part falls as cavities rise, at a fixed hour rate and cycle A curve showing machine cost per part on the vertical axis against the number of cavities on the horizontal axis, at a fixed sell rate and cycle. The curve is a hyperbola: it is highest at one cavity and falls steeply, halving each time cavities double — one cavity four units, two cavities two, four cavities one, eight cavities a half. A shaded band shows that lower yield lifts the whole curve. 1248 cavities cavities (parts per shot) machine cost per part (indexed, 4 cav = 1.00) 4.002.001.000.50 4.002.001.000.50 lower yield lifts the whole curve
Figure 2. At a fixed hour rate and cycle, machine cost per part is the rate divided by cavities and yield — a hyperbola. Doubling cavities halves the machine cost per part, which is why a higher-tonnage, higher-rate press that runs a higher-cavitation tool can still beat a small press per part. Lower yield lifts the whole curve (machine time is wasted on scrap). Indexed to four cavities = 1.00; the shape is exact, the level depends on your rate.
A machined steel plate clamped on a CNC machine bed mid-cut during a production run
A machine cutting steel on the floor. Every hour a machine like this is powered, staffed and occupying floor space is an hour of cost, whether it is cutting a mold or running a molding cycle — which is exactly what an hour rate captures before it is divided across the parts that hour produces. Real production floor; nothing shown is specific to any one customer.
From the tooling floor: when two molders quote the same part at very different prices, do not assume one is padding. Ask three questions before you compare: is the quoted rate with or without the operator and profit, how many productive hours does it assume, and what yield and cavitation is baked in? We have seen a "high" rate turn out cheaper per part because it ran a four-cavity tool at good yield, and a "low" machine-only rate balloon once the operator and a 70% yield were added back. The rate alone never settles it; the rate, the cycle, the cavities and the yield on the same line do.

When this rate build-up fits, and when it does not

This component build-up is the right tool for a steady production run where the press cycles the same job for long stretches: the hour rate times the cycle is a fair model of what the machine actually costs you. It is a sanity check on a molder's quote, a way to see which lever (utilisation, cavitation, yield, labour sharing) moves your piece price most, and a teaching aid for why press size and piece price are not the same thing. It is weaker for very short runs, where setup and changeover dominate and spreading annual cost over "productive hours" understates the real per-part burden; for jobs with heavy secondary operations (assembly, decoration, insert molding) that are not machine time at all; and for shops that book overhead by activity rather than as a flat markup. In those cases use the rate as one input, not the whole answer.

Common mistakes

Sources for the method

Reviewed by the JCH tooling team · updated November 2026

Questions and answers

What is an injection molding machine hourly rate?

It is what it costs to run one injection press for one hour. You build it from the press's own costs spread over its productive hours — depreciation, interest, maintenance, electricity, floor space and the operator — marked up by plant overhead and, for a quote, a margin. Divide the annual total by productive hours and you have the rate. There is no universal number: it depends on your press, your utilisation and your overhead, which is why this tool asks for your figures rather than inventing a default.

How do you calculate the machine hour rate for injection molding?

Cost rate per hour = (depreciation + interest + maintenance + energy + floor + operator labour) × (1 + overhead%) ÷ productive hours. Depreciation = (price − salvage) ÷ life; interest = rate × price × (1 + salvage fraction) ÷ 2; energy = specific energy (kWh/kg) × throughput (kg/h) × electricity price × hours; labour = operators × hours × wage × burden. A sell rate adds margin. The only defaults here are the US industrial electricity price (EIA) and the US median operator wage (BLS), each sourced in its field.

Why does a bigger press cost more per hour?

It costs more to buy (more depreciation and interest per hour), takes more floor space, draws more energy and is often tended at a higher charge. The Q4 2007 Plastics Technology survey shows rates climbing steadily with clamp tonnage. But a bigger press can still cost less per part when it runs a higher-cavitation tool, because piece price divides the rate by the number of cavities.

Does the hourly rate include the operator and profit?

Depends whose rate it is — which is why quotes differ. A machine-only rate excludes both; a quoted rate includes them. The PT Q4 2007 survey put the operator at roughly 9–14% and profit at roughly 5–9% of a quoted mid-press rate. Always ask whether a rate is with or without operator and profit before comparing two of them.

How much of the piece price is machine time?

No fixed percentage — compute it. Machine cost per part = sell rate × cycle ÷ 3600 ÷ (cavities × yield). For a fast, high-cavitation, cheap-resin part the machine share dominates; for a slow, single-cavity engineering-resin part the resin can dominate. In Case A machine time is the larger share; in Case C it balloons past 2.00 per part. Run your own numbers.

Is there a standard or average press rate I can just use?

No current, free, authoritative table exists. Plastics Technology itself says there is "no objective source of average machine-hour rates" by tonnage, and plant-to-plant spread is 50–100%. The newest free structural data point is the 2007 PT survey — too old to quote as current. That is why this calculator ships with no invented press-rate default and builds the rate from your costs.

Ask JCH about press rates and piece price

Not sure what productive-hours number to use, or how shared operator tending changes your rate? Ask our AI assistant. It answers from this website, and our tooling team follows up if you want.

AI assistant. Answers can be wrong; nothing it says is a quote or a promise.

Want a second set of eyes on a molder's quote?

This calculator gives an engineering estimate from your own numbers. Our tooling team can walk a quote with you — checking whether the press rate is with or without operator and profit, what hours and yield it assumes, and whether the cavitation is right for your volume — before you commit to tooling.

Book a 30-min call Send a drawing or quote