First Article Inspection Planner
A first article inspection should account for every requirement on the drawing, notes included, on parts from the cavities your buyer's clause names, and it should file the material certificates and functional test reports the drawing calls for, laid out on the three forms described in the IAQG draft 9102 form instructions. Enter your counts and this planner returns the balloons to place, the cavities and parts to pull, the readings to record, the report sections, and whether a change calls for a full or a partial repeat. It works from public summaries and published supplier clauses rather than the paid AS9102 text, and every count rule it adds on top carries the label our reading.
This is a planning estimate built from counting rules, not a quote and not a reading of your contract. The clauses on your purchase order decide which cavities, how many parts and which forms the real report needs.

How this works
A first article inspection checks every requirement on the drawing against parts made by the production tool and process, before volume begins. Its size comes from three counts that multiply: how many requirements the drawing holds, how many cavities make the part, and how many parts from each cavity get measured. Material and test evidence add sections to the report without adding measurements. The planner keeps those counts apart so you can see which one is driving the workload, and so a buyer and a molder can agree on the scope in numbers before the first trial shot.
Step 1: count the balloons
Every requirement gets a unique number on a marked-up copy of the drawing, and the IAQG draft instructions for Form 3 say each ballooned characteristic must clearly trace to its result line. Count dimensions with their tolerances, feature control frames, surface finish callouts and notes; Net-Inspect's article on automated ballooning names those same categories as what gets identified. Notes are the items people drop. Quality Magazine's guide to building an AS9102 report lists notes alongside dimensions and tolerances among the product characteristics Form 3 must account for. For scale, the Net-Inspect article puts a complex aerospace part at 250 to 500 dimensions.
Repeated callouts are the other trap. A note in the IAQG draft lets one callout that applies to several features, such as a 4X hole, stay a single characteristic, with its results listed one by one or once as a minimum and maximum; any instance found nonconforming then moves to its own line with its measured value. So a 4X callout is one balloon but four places to measure. Enter those extra instances in the optional field: they leave the balloon count alone and raise the readings.
Step 2: classify, then measure everything anyway
Critical, major and minor are defect classes, and the wording most sampling plans still echo comes from the military sampling standards. MIL-STD-105D, posted publicly by Public.Resource.Org, treats a defect as critical when judgment and experience say it is likely to create hazardous or unsafe conditions for the people who use, maintain or depend on the product; as major when, short of critical, it is likely to cause failure or materially cut usability; and as minor when it is unlikely to materially cut usability or departs from standards with little effect on use. In a first article the class does not decide whether a characteristic is measured, because all of them are. It decides the designator column: the IAQG Form 3 instructions include a characteristic designator field for special items the customer defines, such as key characteristics and critical items. The planner reports critical plus major as the designated lines, which assumes your customer marks both, and shows whatever is left after the three classes as unclassified.
Step 3: choose cavities and parts per cavity
Each cavity is its own piece of cut steel, so each is its own source of dimensions, and some buyers tie the first article to the cavity for that reason. The PSEMC supplier instructions for AS9102 ask for the tool number and the cavity ID on the report, and state: “if tool has multiple cavities, the FAI must be performed on each cavity.” Apple Rubber's published first article standard offers a tiered alternative suited to high-cavitation tools. Its Option 1 takes one piece per cavity for molds up to 30 cavities, one piece per cavity from about 30 cavities for molds between 30 and 120, and one piece per cavity from 25% of the cavities above 120. Its Option 2 takes three pieces per cavity on the same tiers.
Two details of that tiered scheme are our reading. The Option 2 middle tier is printed as “approximately 30 pieces sampled” where Option 1 says cavities, and the planner treats both as about 30 cavities, so confirm that line with your buyer. And 25% of a cavity count that does not divide evenly is rounded up, so 150 cavities gives 38 rather than 37.5. The custom option covers buyers who name some other number of parts from every cavity.
Step 4: count the readings
A reading, as this page uses the word, is one number or one pass/fail written down for one feature instance on one part. It is the honest unit for planning inspection time, because a 4X callout measured on three parts is twelve readings even though it is one balloon. The planner multiplies the readings in one full layout by the parts pulled. When a cavity gives more than one part, it can instead run the full layout on the first part only and repeat just the critical and major features on the others; that split is our reading of a sensible economy, not a rule from any source cited here.
Step 5: evidence that is not a dimension
Per the IAQG draft, Form 2 comes into play whenever the design itself specifies a material, a special process or a functional test. Each line names the material or process and its specification, identifies the supplier, and carries a certificate of conformance number; a functional test gets its procedure number and an acceptance report number. On a molded part the typical Form 2 lines are the resin certificate, any colorant or additive certificate the drawing names, any plating, printing or heat-staking process with its own specification, and each functional check written on the print. Count them as certificates and tests. They add report sections without adding readings, but without them the report is incomplete. Form 1 identifies the part, its revision, the drawing and its revision, marks the inspection as full or partial, and carries the sign-offs; the draft adds that the person who approves the report should not be the person who verified it.
Step 6: full or partial, and when to go again
AS9102 Rev B section 4.6, as reproduced in the LMI Aerospace FAI guideline FAI_STD-001 hosted by Sonaca, names six situations in which the affected characteristics, or the whole part, must be inspected again. In plain terms they are: the design moves in a way that touches fit, form or function; the part gets a new maker, process, inspection method, plant, tool or material that could touch those same three things; the numerical control program is edited or carried over to new media; a natural or man-made event may have disturbed the process; corrective action is still needed before an earlier FAI can close; and production has sat idle for two years, with the gap measured from the final manufacturing step before the pause to the first step after it. The same reproduced section allows a partial FAI covering only the changes from a baseline part number, provided every other characteristic conformed last time and is still made by the original processes, and it asks for that baseline part number, its revision and the reason on Form 1.
Buyers set their own lapse clocks. Kaman's FAI questionnaire uses one year or two depending on which quality note the RFQ cites, and the PSEMC clauses SQC 70A, 70B and 70C allow 12, 6 and 24 months. The planner raises the lapse trigger once the idle months exceed the limit you type, which is our reading of how such a limit is counted, and then sizes a partial repeat from the affected characteristics and affected cavities you enter. If the affected count equals the whole drawing, it plans a full repeat.
Worked example: a four-cavity snap-fit housing
A hypothetical housing is molded on a four-cavity tool. Its drawing carries 58 characteristics, notes included: 2 critical, 14 major, 30 minor and 12 unclassified. Two callouts repeat, a 4X boss hole and a 6X rib thickness. The buyer asks for three parts from each cavity, a resin certificate, a colorant certificate and one snap-retention test. The Load the four-cavity housing button fills in these inputs; Load the cavity 3 repair fills in the repeat case at the end.
Three things stand out. The parts-per-cavity choice alone triples the workload: one part per cavity would be 66 × 4 = 264 readings and three parts in full 792, while the split layout holds it to 392, about one and a half times the single-part figure. The repeated callouts add 8 readings per part even though they add no balloons. And a repair confined to one insert, handled as a partial repeat, needs 15 readings instead of a fresh 392, which is the practical payoff of naming the affected features up front. For a high-cavitation contrast, the Load a 64-cavity seal tool button runs a 12-characteristic part on 64 cavities: the tiered Option 1 samples 30 cavities for 360 readings, while a one-part-from-every-cavity clause needs all 64 for 768.
Published counts this page reproduces
| Case | Published rule | This page |
|---|---|---|
| 24-cavity tool, Option 1 | One piece per cavity for molds up to 30 cavities (Apple Rubber) | 24 cavities, 24 parts |
| 24-cavity tool, Option 2 | Three pieces per cavity up to 30 cavities (Apple Rubber) | 24 cavities, 72 parts |
| 64-cavity tool, Option 1 | About 30 cavities for molds between 30 and 120 (Apple Rubber) | 30 cavities, 30 parts |
| 160-cavity tool, Option 1 | 25% of cavities above 120 (Apple Rubber) | 40 cavities, 40 parts |
| 8-cavity tool, every-cavity clause | FAI performed on each cavity (PSEMC SQC 70) | 8 cavities, 8 parts (one per cavity: our reading) |
| 26 idle months, two-year limit | Lapse of two years triggers an update (AS9102 Rev B 4.6 as reproduced by LMI) | Lapse trigger raised |
Where this planner fits among approval routes
| Route | What it proves | Scope as the source states it |
|---|---|---|
| Full first article (this planner) | The production tool and process can make every drawing requirement | Every characteristic, with material and test evidence, on the three forms in the IAQG draft |
| Partial or delta first article | A change did not break the features it could reach | Only the changes from a baseline part number, per the reproduced section 4.6 |
| A contract shop's limited inspection | Key features are in tolerance on early parts | A ceiling of 10 parts and 25 dimensions in the version Protolabs offers |
| PPAP | The whole production process is ready, not just the part | Up to 18 elements, samples “randomly selected from a significant production run usually at least 30 pieces”, and five submission levels (Quality-One) |
| Golden and boundary samples (our explainer) | How the part should look and feel | Appearance limits a drawing cannot spell out |
| Lot inspection (AQL calculator) or a pass/fail validation run (zero-defect sample size) | Each shipment, or one reliability claim | Sampling plans for production lots or test runs, after the first article is approved |
Common mistakes
- Ballooning dimensions and skipping notes. A flash limit or a marking note is a requirement, and leaving it off is how a report looks complete while missing the item that fails in use.
- Mixing parts from different cavities in one bag. Once parts lose their cavity identity, a per-cavity report cannot be built from them.
- Treating 4X as four balloons, or as one reading. Under the IAQG note it can be one characteristic, yet all four instances still get measured.
- Measuring parts that have not settled. Our samples and first articles guide covers conditioning parts before measurement, with the ASTM D955 timing it cites.
- Calling a repeat partial without naming the baseline. The reproduced section 4.6 ties a partial FAI to a baseline part number and a stated reason on Form 1.
- Assuming the lapse clock is two years. The reproduced AS9102 Rev B text says two years, but the buyer clauses cited above run from 6 to 24 months, and the order decides.
Sources for the method. Form 1, 2 and 3 contents, the repeated-callout note and the designator field: IAQG draft Rev C, 9102 form instructions. Re-FAI triggers, partial FAI and the two-year lapse: LMI Aerospace, AS9102 FAI Guideline FAI_STD-001 Rev. L. Every-cavity clause and the 12, 6 and 24-month lapses: PSEMC, AS9102 FAI supplier process steps. Tiered cavity sampling: Apple Rubber, Standard First Article Inspection Report. One- and two-year lapse notes: Kaman, FAI Requirement Determination Questionnaire. Notes on Form 3: Quality Magazine, How to Create an AS9102 First Article Inspection Report. What gets ballooned and the 250 to 500 dimension range: Net-Inspect, How Automated Ballooning Accelerates First Article Inspection. Defect classes: MIL-STD-105D, section 2. PPAP elements, sample run and levels: Quality-One, PPAP. Limited FAI scope: Protolabs, First Article Inspection. All sources were read on November 20, 2026. The multiplication, the split-layout option, the Form 3 per-cavity layout and the rounding are our own.
Reviewed by the JCH tooling team · updated November 2026.
First article planning questions
Do notes on the drawing need their own balloons?
Yes. A general note such as a material callout, a marking instruction or a flash limit is a requirement, so it gets a number and a result line like any dimension. Quality Magazine's AS9102 how-to says notes have to be accounted for on Form 3, and skipping them leaves a report that looks complete while the trickiest requirements go unrecorded.
How many parts should I pull from a multi-cavity mold?
Whatever your buyer's clause names, and get it in writing before the trial. Published supplier rules range from one part out of every cavity to a tiered scheme that samples a subset once the tool passes 30 cavities, sometimes with three parts per cavity. Bag each part by cavity number at the press, since a part with no cavity identity cannot be traced back to its steel.
What goes on Form 2 versus Form 3?
Form 2 holds evidence that something was done to specification: the resin or metal certificate, a plating or heat-treat certificate, the procedure and acceptance report for a functional check. Form 3 holds the measured or attribute result against each numbered requirement. In the IAQG draft form instructions, each Form 2 line has a field for the certificate number, so collect the paper before the report is assembled.
When is a partial FAI enough?
When the previous article passed on every characteristic, the untouched features still come off the same processes as before, and the change touches a known subset. You re-check just those features, and the cover form names the earlier approved part and its revision, plus the reason for going again. If you cannot say which features a change could reach, plan a full repeat instead.
Does a long production gap force a new first article?
It can. The AS9102 Rev B text reproduced in a public supplier guide sets the gap at two years, with the clock running from when production last stopped until it starts again, while individual buyers set their own limits; one published clause family uses 6, 12 or 24 months. The planner raises that trigger when the gap you type is longer than your buyer's limit.
Is a first article the same thing as PPAP?
No. A production part approval package can contain up to 18 elements, from process flow and control plan to measurement studies, and its dimensional element is roughly what a first article delivers. If your customer asks for PPAP, the planner covers only the dimensional and material slices of that package.
Should critical characteristics be handled differently in an FAI?
Every characteristic gets measured either way; the class changes what happens around the number. Critical and key items carry a designator on the result line when the customer defines them and deserve the most capable gauge you have. In our reading they are also the natural candidates for extra pieces per cavity and for a capability study once production starts.
Ask JCH about your first article scope
Describe the part, the cavity count or the change that has you wondering whether a re-inspection is due. The assistant answers from pages published on this site, and after its first answer the chat panel shows an optional box for an email address.
Replies are machine-written from site pages. They can miss details of your drawing or contract, so use them to frame questions, not to settle a contract.
Scoping a first article for a new tool?
Send the drawing revision, the cavity count and the inspection clause from the order. We will go through the balloon list, the parts to pull from each cavity and the certificates to collect with you, so the scope is agreed in numbers before the trial.
Book a free 30-minute first consultation Drawing review questions