Bill of materials: what a factory needs on your BOM to quote and build it

A spreadsheet of part names is a start, not a BOM a factory can quote. Here is what each line needs, how EBOM and MBOM differ, and the mistakes that turn into change orders.

Filed under Engineering and services

Short answer: A bill of materials (BOM) is the list of every part, material and sub-assembly, with quantities, needed to build one finished product. For a factory quote, the BOM has to do more than list names: each line needs a part number and revision, a quantity per assembly, the exact material or manufacturer part number, approved alternates, and a note on who buys it. A vague BOM gets a vague quote, and the gaps come back later as change orders and delays.

The first thing we ask for on a new program, after the drawings, is the bill of materials. The first version we receive is usually a spreadsheet with part names, a few quantities and a column of question marks. That is a fine start for a design team. It is not enough for a factory to quote against, buy against or build against. This note covers what a bill of materials is, the kinds you will hear about, what each line needs before a factory can price it, and the mistakes we see most often.

What a bill of materials is

Wikipedia describes a BOM as the list of raw materials, sub-assemblies, intermediate assemblies, components, parts and quantities needed to make an end product, and notes that "A BOM may be used for communication between manufacturing partners or confined to a single manufacturing plant." The first half of that sentence is the one that matters when you work with an outside factory. Your BOM is a contract document between companies. Every line the factory cannot interpret becomes an email, a guess, or a price padded to cover the guess.

A BOM has a structure. A single-level BOM lists only the direct children of one assembly. A multi-level or indented BOM shows the whole tree: "An indented BOM (or structural parts list) that displays the highest-level item closest to the left margin and the components used in that item indented more to the right." For anything with sub-assemblies, send the indented version. A factory pricing a product needs to see which parts go into which sub-assembly, because that drives the labor steps, the test points and the packaging.

EBOM, MBOM and the BOM the factory builds

You will hear several names. Wikipedia lists four common views of the same product: as designed (engineering BOM), as ordered (sales BOM), as built (manufacturing BOM) and as maintained (service BOM).

Two of them matter on most programs:

Neither is the record of what was actually used. "The MBOM can be viewed as the ingredients in a recipe to make a cake, where as "as built" refers to the actual materials that were consumed to make the cake." If a lot fails in the field, you want to know which revision, which resin lot and which alternate part went into that lot. That record comes from the factory's lot traceability, not from the BOM, so ask for both.

What each line needs before a factory can quote

For each BOM line, the factory needs enough to buy or make the item without asking you. At minimum:

  1. Your part number and revision. "A part number unambiguously identifies a part design within a single corporation, sometimes across several corporations." Inside your company that is enough. Outside it, pair it with a revision letter, and keep the revision in step with the drawing.
  2. Description in plain words, for example "housing, top" or "screw, M3 x 8, pan head".
  3. Quantity per assembly and unit of measure. "2 each", "0.15 m", "12 g". Bulk materials like adhesive, wire and potting need a quantity, not "as required", or nobody can cost them.
  4. Material or specification. For a molded part, the resin grade and color, not just "ABS". For a sheet-metal part, alloy, temper, thickness and finish. For fabric, the composition and weight.
  5. Make or buy. Whether the factory makes the part (molding, machining, sheet metal) or buys it. Made parts need a drawing reference; bought parts need a manufacturer and part number.
  6. Manufacturer and manufacturer part number for bought parts, plus any approved alternates. If you name only one source, you have signed up for that part's lead time and allocation risk.
  7. Who supplies it. Factory-sourced, customer-supplied, or consigned. Customer-supplied parts have to arrive on time and in the right quantity, and the quote should say who carries the scrap allowance.
  8. Compliance flags that apply, such as RoHS for electronics or food-contact for a resin, so the buyer does not substitute a part that fails them.

The design for manufacturability review is the natural place to fix these gaps, before tooling, while changes are still cheap.

Electronics BOMs have their own rules

"In electronics, the BOM represents the list of components used on the printed circuit board (PCB)." An assembly house will quote your PCB from three files together: the Gerbers, the pick-and-place file and the BOM. Every placed part needs a reference designator (R12, C4, U1) that matches the board, a value and package, and a manufacturer part number. "10k resistor" is not a line item; the house needs the package size, tolerance and an orderable part.

A row of SMT pick-and-place machines with component reel feeders loaded in a clean, brightly lit assembly room
An SMT line at a partner facility. Every reel on these feeders traces back to a BOM line with a reference designator and a manufacturer part number.

Variants need explicit marking. "Parts which will not be assembled at all in one or more variants are typically marked as "DNP" (for "do not populate" or "do not place") in the affected variants." If you build two versions of one board, say so on the BOM rather than in an email, or someone will build every variant fully populated. Our notes on turnkey PCB assembly and the electronics step cover what else the line needs before the first build.

The mistakes we see most

  • The BOM and the drawing disagree. The drawing is at revision C, the BOM still lists revision B parts. The factory will ask which one wins. Decide that rule in advance: in most programs the released drawing and BOM are released together, and neither moves alone.
  • Missing consumables and packaging. Screws, labels, foam, polybags, cartons and inserts are often not on the engineering BOM. They are real cost and real lead time. The packaging step is where most of them are confirmed.
  • "Or equivalent." Without a named alternate, "or equivalent" means the buyer chooses. If a substitution would matter to you, list the approved alternates and say that any other substitution needs your written approval.
  • Changes sent as emails. A BOM change after release should go through the same change control as a drawing. Our note on the engineering change order covers what that document should say when the factory is outside your company.
  • No quantities for bulk materials. A line that says "glue, as required" cannot be costed and will be either padded or forgotten.
Two CNC lathes with open control cabinets on a green factory floor marked with yellow safety lines
Made parts, like turned and machined components, need a drawing reference and a material on the BOM, not just a name.

How to send a BOM for a quote

Send one file per product, in a spreadsheet the factory can sort, with the columns above and one row per part number per assembly. Put the drawing revision and the BOM revision in the file name and on the first row. Mark the parts you will supply, the parts with a mandated source, and any parts still in design. If you only have a sketch or a sample, say so. A factory can help build the first BOM, but the quote will carry assumptions you should read line by line.

Where Jack fits

JCH runs manufacturing programs at vetted partner factories. Jack reviews the drawings and the bill of materials together at the drawing and CAD step, flags lines the factory cannot price as written, and sends the questions back before the quote rather than after the deposit. JCH itself holds no certification. Where a program needs ISO, UL or third-party testing, Jack matches it to partner facilities and accredited labs that hold them.

If you have a BOM and a set of drawings, send them to Jack and he will tell you which lines are ready to quote and which need another pass.

Straight answers

What is a bill of materials?

A bill of materials (BOM) is the list of every raw material, part, sub-assembly and quantity needed to make one finished product. In manufacturing it is the document a factory quotes, buys and builds against, so each line needs a part number, revision, quantity, material or manufacturer part number, and who supplies it.

What is the difference between an EBOM and an MBOM?

An engineering BOM (EBOM) reflects the product as designed, organized by the design structure. A manufacturing BOM (MBOM) lists everything needed to build a complete, shippable product, including packaging, labels and consumables, organized the way the factory builds it.

What should a BOM include for a manufacturing quote?

For each line: your part number and revision, a plain description, quantity per assembly with a unit of measure, the material or specification, whether the part is made or bought, the manufacturer and manufacturer part number with approved alternates for bought parts, who supplies it, and any compliance requirements.

What does DNP mean on a BOM?

DNP stands for do not populate (or do not place). It marks a part that is not assembled in one or more variants of a product, most often on printed circuit board assemblies that are built in several versions from one board design.

Should a BOM change go through an engineering change order?

Yes. Once a BOM is released to a factory, changes should go through the same change control as the drawings, with an engineering change order that states the old and new revision, the effective point and what happens to existing stock and work in progress.

bill of materialsBOMEBOMMBOMmanufacturing BOMengineering BOMpart numberDNPPCB assembly BOM

How this note was made: researched and drafted with AI assistance, checked against the sources listed below and edited at JCH Design & Manufacturing.